Tuesday, September 6, 2011

Structural Support Defined & Implemented

By last Thursday the structural engineer working with our architect and construction management team provided a plan to compensate for the missing columns and beams so that demolition work could continue. The Donnelly crew worked Saturday in order to dig footings for the new load bearing walls; their inspection passed today. Weather permitting, footings will be poured tomorrow. In the mean time, wall and ceiling restoration is being completed in the bedrooms in preparation for new paint and trim. We should know by Friday what exposing existing plumbing under the slab reveals.