Monday, November 28, 2011

New Kiwanis Demolition



The majority of the walls have been taken down in the second cottage under construction. The beam that was missing in the first cottage has been revealed in this cottage. The architect is verifying its structural integrity with the engineers. In the mean time, the plumbers are doing their thing and the work in the corridors and bedrooms is progressing. The masons are taking advantage of the good weather.

Monday, November 14, 2011

Move In Day - Farrow Cottage
















The Residential and Operations staff are working side by side with the residents to move the boys into their newly renovated space. We can't tell who is more excited - the residents or the staff. Pictured is Phil Errico, Residential Director and Nabate and Tarik, Farrow residents.

Thursday, November 10, 2011

TCO Issued!

Today the Fire Inspection and Final Building Inspection passed - we have a temporary certificate of occupancy for the New Farrow cottage. The final certfiicate of occupancy won't be issued until all four cottages are completed and the job is done. The move is still on for Monday, November 14!

Wednesday, November 9, 2011

News from our Project Superintendent

As you know we passed our electrical inspection for a TCO.

Today we passed our plumbing for our TCO.

Tomorrow is building and fire.

We will follow up with a punch list. I am trying to catch as many things as possible to narrow our final punch list down to only a handful of items.

Our carpet is being switched out today. We are also having the Core flooring completed tonight as well.

All in all I think we're in good shape for an on time move.


Harold J. Stempert, Jr.
Project Superintendent
Donnelly Construction

Tuesday, November 8, 2011

Final Electrical Inspection

We passed the new Farrow cottage final electrical inspection today.

Monday, November 7, 2011

Farrow Cottage Final Inspection Schedule

The final electrical inspection is scheduled for Tuesday, November 8; final plumbing inspection is scheduled for Wednesday, November 9; fire and final for TCO is scheduled for Thursday, November 10. The move in date is still Monday, November 14.