Tuesday, September 20, 2011

Interior Framing



The bulk of the interior framing is complete. You can actually see the deliniation of the three bathrooms, storage closet, and kitchen space. We are awaiting receipt of light guage structural metal that had to be special ordered as a result of the structural design changes. Delivery is scheduled for tomorrow and then framing will be completed. The main corridor and living room at the end of the hallway are sheetrocked, spackled, and ready for paint. The two solar tubes have been delivered and their exact placement needs to be defined with the help of our architect.