Rough Plumbing and Concrete

The plumber is finishing up the rough plumbing today and the inspection is scheduled for Monday. The weather didn't cooperate this week so the concrete pour has been moved to Monday and Tuesday of next week. We believe the schedule impact of the structural changes will be about a week and a half and the dollar impact for all four cottages will be about $35k. Fortunately our budget has a contingency that can absorb the hit. The sheetrock has been delivered and by end of next week we should start to see the walls going up.