Thursday, February 16, 2012

New Schley Update

The following inspections have passed to date: Exterior footing, partial slab, partial footing under multi-purpose room, underground plumbing, interior slab/haunch.

Interior and exterior concrete pour scheduled for today. Framing scheduled to be completed Wednesday. Plumbing and electric will be done concurrent with framing. Bedroom door frames are installed and painting started. Cupola should be completed end of next week. HVAC work starts after cupola is completed. On or ahead of schedule for this phase of the project.