Thursday, February 23, 2012

New Schley Udpate

On schedule for rough plumbing and electrical inspections next Thursday. Then a framing inspection the next day. All of the concrete work is complete, including the new sidewalks (thanks in part to the great winter weather we're experiencing). Brick work to be completed tomorrow. Cottage turn-over date holds firm at March 29, 2012.