Thursday, March 22, 2012

Final Week for New Schley

We are still on schedule for a Thursday, March 29 cottage turn-over. The carpets are being installed today and tomorrow. The flooring in the rest of the cottage should be completed today. Solid surfaces are being installed today. Final painting and touch-up on Saturday. The final plumbing and electric inspections are scheduled for Monday. Final building for the TCO is scheduled for Tuesday. The cleaning crew will be working on Wednesday. The boys move in on Thursday. Friday demolition for the final cottage, Osborne, commences.