Thursday, January 5, 2012

New Kiwanis Update

We passed the rough electrical inspection on 12/28 and the plumbing and framing inspections on 1/3/12. Sheetrock is being installed and interior doors are being hung. Our Construction Manager reported today they are about 2 weeks behind their schedule due to performance problems with their framing sub-contractor. The new anticipated date for completion is Wednesday, January 25. We are still on target for LEED Silver.