Thursday, October 27, 2011

1 Additional Week Delay in Completion of Cottage 1



We were notified this morning that the target date of 11/7 for move-in has been pushed out to 11/14. This was primarily due to longer than expected lead times and delays in the receipt of material for the energy recovery ventilators, pedimat, lighting, and solid surfaces. Donnelly is looking to make up this week plus the other 3 weeks that were delayed due to structural issues in the next 3 cottages. Outside, the bricks that were removed during demolition are being reinstalled in the new exterior wall. Work on interior finishes continue.