Wednesday, July 27, 2011

Construction Preparation

On Monday, August 1 construction will begin in the Matinee Theater second floor and McNally. Our Construction Supervisor Harold Stempert will be on-site tomorrow and Friday to plan and stage the work. Materials will be delivered on Monday and subcontractors will commence work. All subcontractors will wear photo identification badges and sign in and out with the Construction Supervisor daily. All individuals performing work on campus will be provided a safety orientation and will receive information about special considerations unique to working at Bonnie Brae. If you have any concerns or questions feel free to contact Ann Zouvelekis on 908-647-4702. The hallway in McNally behind the cafeteria that leads to Farrow cottage will be closed starting Monday. There will still be access to both sets of exterior doors in that hallway but the 20 feet of hall connecting the kitchen service entrance and the sprinkler room will be partitioned off permanently. This area is to become the new mechanical room. Work on the Health Office kitchen area will follow, probably starting the end of next week or the following week.