Thursday, October 6, 2011

More Inspections Scheduled

The electrical inspection is scheduled for this week and the plumbing and framing inspections are scheduled for mid-next week. Painting of the bedrooms is scheduled to commence on Monday. The structural design changes have all been implemented. The silver lining in this whole change is that the design is actually improved; the absence of the missing column enhances the open floor plan that now exists. Good news received from the township Building Department - our proposed change to the insulation plan has been approved, resulting in an anticipated savings of $25k.