Thursday, March 22, 2012
Final Week for New Schley
We are still on schedule for a Thursday, March 29 cottage turn-over. The carpets are being installed today and tomorrow. The flooring in the rest of the cottage should be completed today. Solid surfaces are being installed today. Final painting and touch-up on Saturday. The final plumbing and electric inspections are scheduled for Monday. Final building for the TCO is scheduled for Tuesday. The cleaning crew will be working on Wednesday. The boys move in on Thursday. Friday demolition for the final cottage, Osborne, commences.
Monday, March 12, 2012
Cupola complete

The renovations to the cupola have been completed. The new cupola provides a semi conditioned space in the attic. Constructed using insulated low e glass and insulated panels with louvers that allow in fresh air this new design replaces the open cupola that attracted unwanted wildlife and also was completely exposed to weather.
Thursday, March 1, 2012
New Sidewalks
Wednesday, February 29, 2012
Update from our Construction Manager
We have passed our plumbing & electrical inspections. We are looking for Framing tomorrow afternoon or Friday.
Tomorrow we set the shower pans, tie into the manifold and apply nail plates. and set ADA shower blocking.
Drywall begins following framing inspection.
Tomorrow we set the shower pans, tie into the manifold and apply nail plates. and set ADA shower blocking.
Drywall begins following framing inspection.
Thursday, February 23, 2012
New Schley Udpate
On schedule for rough plumbing and electrical inspections next Thursday. Then a framing inspection the next day. All of the concrete work is complete, including the new sidewalks (thanks in part to the great winter weather we're experiencing). Brick work to be completed tomorrow. Cottage turn-over date holds firm at March 29, 2012.
Thursday, February 16, 2012
New Schley Update
The following inspections have passed to date: Exterior footing, partial slab, partial footing under multi-purpose room, underground plumbing, interior slab/haunch.
Interior and exterior concrete pour scheduled for today. Framing scheduled to be completed Wednesday. Plumbing and electric will be done concurrent with framing. Bedroom door frames are installed and painting started. Cupola should be completed end of next week. HVAC work starts after cupola is completed. On or ahead of schedule for this phase of the project.
Let's hope the weather continues to cooperate!
Interior and exterior concrete pour scheduled for today. Framing scheduled to be completed Wednesday. Plumbing and electric will be done concurrent with framing. Bedroom door frames are installed and painting started. Cupola should be completed end of next week. HVAC work starts after cupola is completed. On or ahead of schedule for this phase of the project.
Let's hope the weather continues to cooperate!
Monday, January 30, 2012
Move In Day - Kiwanis Cottage



Staff and kids are working together to move into the new Kiwanis cottage today. The space features a whole new color scheme selected by residents with help from our Interior Designer Jeanne Barbet. The Donnelly team worked through the weekend to ensure the cottage was ready for our guys. Special recognition goes to Harold Stempert for his tireless dedication to the project.
Subscribe to:
Posts (Atom)