Thursday, February 23, 2012
New Schley Udpate
On schedule for rough plumbing and electrical inspections next Thursday. Then a framing inspection the next day. All of the concrete work is complete, including the new sidewalks (thanks in part to the great winter weather we're experiencing). Brick work to be completed tomorrow. Cottage turn-over date holds firm at March 29, 2012.
Thursday, February 16, 2012
New Schley Update
The following inspections have passed to date: Exterior footing, partial slab, partial footing under multi-purpose room, underground plumbing, interior slab/haunch.
Interior and exterior concrete pour scheduled for today. Framing scheduled to be completed Wednesday. Plumbing and electric will be done concurrent with framing. Bedroom door frames are installed and painting started. Cupola should be completed end of next week. HVAC work starts after cupola is completed. On or ahead of schedule for this phase of the project.
Let's hope the weather continues to cooperate!
Interior and exterior concrete pour scheduled for today. Framing scheduled to be completed Wednesday. Plumbing and electric will be done concurrent with framing. Bedroom door frames are installed and painting started. Cupola should be completed end of next week. HVAC work starts after cupola is completed. On or ahead of schedule for this phase of the project.
Let's hope the weather continues to cooperate!
Monday, January 30, 2012
Move In Day - Kiwanis Cottage



Staff and kids are working together to move into the new Kiwanis cottage today. The space features a whole new color scheme selected by residents with help from our Interior Designer Jeanne Barbet. The Donnelly team worked through the weekend to ensure the cottage was ready for our guys. Special recognition goes to Harold Stempert for his tireless dedication to the project.
Wednesday, January 25, 2012
Count down to New Kiwanis Opening
Flooring is installed. Solid surfaces and fixtures are in. Curtains are hung. Finishing touches are in the works. The final electric and plumbing inspections are scheduled for tomorrow, Thursday, January 26. The final building, fire, and TCO are scheduled for Friday, January 27. Professional cleaners will be working Saturday to ready the brand new cottage for the guys.
Thursday, January 19, 2012
New Cottage Turn Over Date
Due to delays in material deliveries the new cottage turn over date for New Kiwanis is Monday, January 30. Demolition of Old Schley/New Osborne is now set for Tuesday, January 31.
Thursday, January 5, 2012
New Kiwanis Update
We passed the rough electrical inspection on 12/28 and the plumbing and framing inspections on 1/3/12. Sheetrock is being installed and interior doors are being hung. Our Construction Manager reported today they are about 2 weeks behind their schedule due to performance problems with their framing sub-contractor. The new anticipated date for completion is Wednesday, January 25. We are still on target for LEED Silver.
Monday, December 12, 2011
Old Farrow/New Kiwanis Update
The slab inspection passed last Wednesday. The interior slab, sunken bathroom floors, pedimat impression, footings, laundry and sidewalk were poured on Thursday and Friday. Framing begins tomorrow.