Thursday, March 22, 2012

Final Week for New Schley

We are still on schedule for a Thursday, March 29 cottage turn-over. The carpets are being installed today and tomorrow. The flooring in the rest of the cottage should be completed today. Solid surfaces are being installed today. Final painting and touch-up on Saturday. The final plumbing and electric inspections are scheduled for Monday. Final building for the TCO is scheduled for Tuesday. The cleaning crew will be working on Wednesday. The boys move in on Thursday. Friday demolition for the final cottage, Osborne, commences.

Monday, March 12, 2012

Cupola complete



The renovations to the cupola have been completed. The new cupola provides a semi conditioned space in the attic. Constructed using insulated low e glass and insulated panels with louvers that allow in fresh air this new design replaces the open cupola that attracted unwanted wildlife and also was completely exposed to weather.



Thursday, March 1, 2012

New Sidewalks

Last night's rain tested our new sidewalks and we're happy to report positive results. No puddles! Plus, framing inspection passed today.