The majority of the walls have been taken down in the second cottage under construction. The beam that was missing in the first cottage has been revealed in this cottage. The architect is verifying its structural integrity with the engineers. In the mean time, the plumbers are doing their thing and the work in the corridors and bedrooms is progressing. The masons are taking advantage of the good weather.
Monday, November 28, 2011
Monday, November 14, 2011
Thursday, November 10, 2011
TCO Issued!
Today the Fire Inspection and Final Building Inspection passed - we have a temporary certificate of occupancy for the New Farrow cottage. The final certfiicate of occupancy won't be issued until all four cottages are completed and the job is done. The move is still on for Monday, November 14!
Wednesday, November 9, 2011
News from our Project Superintendent
As you know we passed our electrical inspection for a TCO.
Today we passed our plumbing for our TCO.
Tomorrow is building and fire.
We will follow up with a punch list. I am trying to catch as many things as possible to narrow our final punch list down to only a handful of items.
Our carpet is being switched out today. We are also having the Core flooring completed tonight as well.
All in all I think we're in good shape for an on time move.
Harold J. Stempert, Jr.
Project Superintendent
Donnelly Construction
Today we passed our plumbing for our TCO.
Tomorrow is building and fire.
We will follow up with a punch list. I am trying to catch as many things as possible to narrow our final punch list down to only a handful of items.
Our carpet is being switched out today. We are also having the Core flooring completed tonight as well.
All in all I think we're in good shape for an on time move.
Harold J. Stempert, Jr.
Project Superintendent
Donnelly Construction
Tuesday, November 8, 2011
Monday, November 7, 2011
Farrow Cottage Final Inspection Schedule
The final electrical inspection is scheduled for Tuesday, November 8; final plumbing inspection is scheduled for Wednesday, November 9; fire and final for TCO is scheduled for Thursday, November 10. The move in date is still Monday, November 14.